Exterior Framing

Exterior Framing

I spent a few days on site last week. Got to hang out with the carpenters and carry some heavy stuff!

photo

Framing prep

The foundation anchors are placed to support the new headers holding up the first and second story floors.

Those headers will hold joists that hold up the (currently missing) south wall.

Once the walls are up, we add sheer walls (a thin layer of wood) and the house has a dry shell.

It’s been over a year since it’s had a dry shell!

Design

This week we’re also making final design decisions and ordering lots of items: fixtures, tile, cabinetry, flooring,

Rough in

We’re planning to start rough in electrical, plumbing, and HVAC. These are not “pretty” updates but will lead to some amazing pretty photography soon.

Pacing of capital

We’ve got our first bank reimbursement and planning the second. We’re working closely with the contractor to get a timeline of draws …